Jeff Green | Aug 29, 2013
The septic system for the Granite Ridge Education Centre, currently under construction in Sharbot Lake, has been the subject of consultation between the Limestone District School Board and the Ontario Ministry of the Environment for a year.
Because the school is located within 300 metres of the west basin of Shabot Lake, which has been identified as a Trout Sensitive Lake by the province, an environmental compliance approval from the ministry was needed before the septic system could be constructed.
On August 23, that approval was granted.
Sarah Dick, Senior Environmental Officer at the Kingston MoE office, said in an email: “On August 23, 2013, the Environmental Compliance Approval for the Granite Ridge Education Centre was issued.
The approval permits the establishment of sewage works for the collection, transmission, treatment and subsurface disposal of domestic sewage, with a rated capacity of 17,000 litres per day. The new system is equipped with phosphorus treatment, which is a significant improvement to the previous system.”
The septic system will need to be constructed and approved before the new school will be able to receive an occupancy permit from the Central Frontenac building department.
The Limestone Board is aiming to have the building ready for students in early November.
More Stories
- All Candidates Meeting in Verona
- Summer Kickoff Music Festival’ Returns to South Frontenac
- Election 2025 Candidate Danielle Rae
- Election 2025 Candidate Michelle Foxton
- 1800s Blacksmithing Comes Alive at the South Frontenac Museum
- Tay Valley Choir Celebrates 20th Anniversary
- Mike’s Pizza in Sydenham
- South Frontenac Approves A New Official Plan
- CF Council Wants To Increase Severances To Stimulate Growth
- Annual Fool's Plunge